• City of Pasadena, CA – SR-710 Mitigation Project Traffic Control and Monitoring System ITS Phase II
Modified/upgraded traffic signals, pedestrian signals, street lighting, and vehicle detection at 80 intersections. Installed CCTV cameras, video detection components, and ADA truncated tiles.
Placed 47,000 feet of conduit.
Installed 380 pull boxes.
Installed 746 inductive loops.
Installed 164 traffic signal and pedestrian signal heads.
Replaced 348 pedestrian pushbuttons.
Set 21 new poles.
Placed 284,000 feet of wire or cable.
Installed 21 video detection systems.
• City of Beverly Hills, CA – Phase 2 Fiber Optic Municipal Area Network Ring
Install conduit, pull boxes and cable throughout central business district. Install cabinets at hubs. Interconnected 102 locations.
Placed 10,400 feet of outside plant conduit with innerduct.
Placed 6,200 feet of interior metallic conduit.
Placed 137,000 feet of fiber optic cable.
Install fiber optic patch panels at 102 locations.
Splice 1,200 fibers cable to cable.
Spliced 2,900 fibers cable to pigtail.
• City of Los Angeles, CA - Mid-Wilshire District ATCS System
Installed Automated Traffic Surveillance/Control and Adaptive Traffic Control System. Modified/upgraded traffic signals, pedestrian signals, street lighting, and vehicle detection at 110 intersections. Installed CCTV cameras.
Placed 26,000 feet of conduit.
Installed 470 pull boxes.
Installed 570 inductive loops.
Installed 890 traffic signal and pedestrian signal heads.
Replaced 3,200 LED traffic signal modules.
Set 42 new poles.
Placed over 300,000 feet of wire or cable.
• State of California – Caltrans Route 1 Adaptive Signal Control System
Signal Control and CCTV systems from Long Beach to Malibu
Placed 44,000 feet of conduit.
Installed 1,180 pull boxes or splice vaults.
Installed 200 inductive loops.
Set 19 CCTV Poles and CCTV camera equipment.
Installed communication equipment at 126 locations.
Installed data/video communications equipment at Hubs, RTMC, TMC
Set 21 new poles.
Placed 245,000 feet of wire or fiber optic cable.
Splice 1,812 fiber optic pigtails to cable.
Splice fiber optic cable at 93 locations
• County of Santa Clara, CA – Silicon Valley Intelligent Transportation System West Corridor
Installed Automated Traffic Management System around airport. Install conduit, pull boxes and cable. Install cabinets at hubs.
Placed 47,000 feet of conduit.
Installed 237 pull boxes or splice vaults.
Installed CCTV cameras and equipment.
Installed data/video communications equipment at Hubs, TMC
Placed 60,000 feet of wire or fiber optic cable.
Splice fiber optic pigtails to cable and cable to cable at 12 locations
• Caltrain Peninsula Corridor Joint Powers Board, CA – CCTV System and Audible Signs
Installed video surveillance system at San Francisco, San Mateo, Mountain View and San Jose Caltrain Stations. Install central communication equipment at San Carlos Center.
Install conduit and pull boxes throughout station, platforms and in remote areas.
Install cabinets, electrical service and infrared lighting.
Install 142 cameras.
Install baseband and IP video system components.
Install audible signage and system